Construction of the Islamabad Expressway Service Road East has moved past 41 percent, with work advancing on several stretches between Faizabad and Gulberg at once.

The Capital Development Authority says the project covers an 8.5 km dual carriageway and is being accelerated on instructions from the interior minister and CDA leadership.
All 153 piles needed for the underpass have now been completed, and slab work there is finished. Retaining walls for Ramp A and Ramp B are still under construction, while excavation, sub-grade and sub-base layers, bridge culverts and drainage work continue. Several culverts are in their final stages.
The project is converting the eastern service road into a six-lane dual carriageway. An enforcement drive is also under way to remove illegal structures and encroachments along the route, with more than 100 buildings demolished or sealed earlier in the month.
CDA Chairman Sohail Ashraf says the finished road should ease pressure on the Islamabad Expressway and improve access for residents, while also cutting journey times and fuel use by keeping local traffic off the main route.
Although the latest progress report gave no firm date, Interior Minister Mohsin Naqvi said this week the scheme should be completed within two months, with around 40 percent progress reported and a gas pipeline relocation issue resolved. On that timetable, the upgraded road could open around early 2027.